fixed bug in schedWindow resizing strategy, where earlier it was stopping after checking if the first task in the queue can be scheduled in the next offer cycle. Changed baseScheduler to store the schedWindowResizingStrategy instead of the criteria. Retrofitted the scheduling policies to use the scheduling window resizing strategy directly from baseSchedRef.
This commit is contained in:
parent
3ebd7b0c7e
commit
435c4ca1bc
6 changed files with 20 additions and 21 deletions
|
@ -60,13 +60,13 @@ type BaseScheduler struct {
|
|||
// Size of window of tasks that can be scheduled in the next offer cycle.
|
||||
// The window size can be adjusted to make the most use of every resource offer.
|
||||
// By default, the schedulingWindow would correspond to all the remaining tasks that haven't yet been scheduled.
|
||||
schedulingWindow int
|
||||
schedulingWindow int
|
||||
|
||||
// Criteria to resize the schedulingWindow.
|
||||
schedWindowResizeCrit schedUtils.SchedulingWindowResizingCriteria
|
||||
// Strategy to resize the schedulingWindow.
|
||||
schedWindowResStrategy schedUtils.SchedWindowResizingStrategy
|
||||
// Window of tasks that the current scheduling policy has to schedule.
|
||||
// Once #schedWindow tasks are scheduled, the current scheduling policy has to stop scheduling.
|
||||
schedWindow int
|
||||
curSchedWindow int
|
||||
}
|
||||
|
||||
func (s *BaseScheduler) init(opts ...schedPolicyOption) {
|
||||
|
@ -78,7 +78,7 @@ func (s *BaseScheduler) init(opts ...schedPolicyOption) {
|
|||
}
|
||||
s.running = make(map[string]map[string]bool)
|
||||
s.mutex = sync.Mutex{}
|
||||
s.schedWindowResizeCrit = "fillNextOfferCycle"
|
||||
s.schedWindowResStrategy = schedUtils.SchedWindowResizingCritToStrategy["fillNextOfferCycle"]
|
||||
}
|
||||
|
||||
func (s *BaseScheduler) SwitchSchedPol(newSchedPol SchedPolicyState) {
|
||||
|
|
Reference in a new issue